Shantou · China +86 133 6387 9944 ISO 9001 · EU 10/2011 · RoHS joe@8pck.com
Home / Custom
Custom development

Copy an Existing Bottle, or Start From a Drawing

Two very different paths. Either we match your pack against 3,000+ existing moulds — no tooling, 1,000 pcs per colour — or you commission a new mould, which is a capital cost: from USD 850 for one simple blow-moulded bottle, and 10,000–21,500 for a four-part assembly in the small band (16,500–37,000 in the medium band). Custom tooling only pays back on repeat volume; below a few thousand pieces a year the stock route is almost always the right answer.

Process

Five Stages, Fixed Durations

If a stage slips, you hear it the same week, not at the ship date.
01
BriefSend a drawing, a sample photo or a reference bottle. Tell us the volume and the market.
02
DFMWe check wall thickness, neck, demoulding and packing — and say what will not work.
03
QuotationTooling (if any), unit price, MOQ, lead time. One page, no ranges.
04
T1 sampleFirst samples in 25 days. You test fill, cap torque and drop.
05
Production30 days from approved sample. Photos before loading.
Tooling

What a New Mould Actually Costs

ItemDetailCostTime
Blow mould (new shape)Single cavity, steelfrom USD 85015–20 days
Injection mould (cap)Multi-cavityfrom USD 3,70025–30 days
Mould modificationNeck, weight or engravingfrom USD 3207–10 days
Existing mould3,000+ on the shelfNo charge—

These are per-mould figures, not project totals. A new pack usually needs more than one mould, plus trial samples and often a second cavity — budget the project, not the line item. Mould ownership and exclusivity are agreed in writing before the first payment.

Before You Commission a Mould

A mould is a capital cost that sits in front of the unit price. It only makes sense when the volume is there to absorb it — so we say this early rather than after a drawing review.

Annual volumeWhat we recommendTooling, in our shop
Under 3,000 pcsStock mould, or a stock shape with decorationNo tooling; 1,000 pcs per colour
3,000–10,000 pcsOne cavity on a new shape, if the design truly needs itUSD 850–9,500 per mould; 15–40 days
10,000–30,000 pcsTwo cavities; consider a second colourAbout 1.6× a single-cavity mould
Over 30,000 pcsMulti-cavity, dedicated line timeAbout 2.6× and up; needs a volume commitment

These are ranges from our own recent orders, not an industry standard — another factory may quote half or double, and both can be honest. A four-part assembly changes the arithmetic: USD 10,000–37,000 of tooling depending on part size is normal, and it does not shrink because the first order is small. If the launch is a test, start on a stock pack and move to the custom one when the volume is proven — that is the lower in unit cost path, and we will say so.

Not Sure Whether a Mould Exists?

Send a photo of the bottle you want copied. We check the shelf the same day.

Send a Photo →

Is the Design Yours?

Then the first question is who else sees the drawing. Our NDA is one page, and the tool stays yours.

Confidentiality and NDA →

How the Joint Is Engineered

Wall, seal groove, formula compatibility and the test plan — the four pages we send before a drawing review.

Custom Mould Development

DFM note, tool design, T1, modification — and who pays for the tool.

How a Mould Is Developed →

Who Invoices You

8PCK is the export desk; the contract and the invoice come from CXWN. Here is why.

Read the Arrangement →

Which Process Makes Your Pack?

Injection, ISBM, extrusion blow, the tool shop and decoration — what each can and cannot hold.

More Than One Piece?

Four parts, two seals and a metal finish change the tooling plan — start with the multi-part guide.

Multi-Part Bottles →
QUOTE ✆
WhatsApp Get a Quote →